Video Description

This lesson focuses on how to perform quality assurance. Quality assurance validates the process not the product and creates change requests and project management plan updates. [toggle_content title="Transcript"] Now we finish the planning stage. It only has one process, plan quality management. Now we are under the executing stage so we are actually performing work so its perform quality assurance. Performing quality assurance validates the process not the product. You are more concerned about making sure the process is correct. You are not concerned about the product at this point. This creates, change requests, project management plan updates. It's inside the project management plan which we just created. This as you remember details the methodologies for quality assurance and continuous process improvement. Remember the process improvement plan, so it must align the project within the organization. If you can imagine if your company is CMMI or OPM3, you have seven processes that have to be met to conform with how your company does business. Quality matrix also just created from the previous process defines the characteristic and variables that are measured and provides the details of acceptable variances. If you can remember, if your standard is 95 percent, and its plus or minus five percent, if it is 89 percent, it fails. If its 90 percent, its within tolerance, its fine. Or another example, if your tolerance is 90 percent plus or minus five percent. You reach that 90 percent goal and you keep going. You reach 95 percent you are still good, you go to 96 percent, now you are gold plating cause you are doing more than what was required. Quality control measurement is another input. Provides the quality criteria and the procedures. The tools for perform quality assurance are quality management and control tools. This evaluates the data against the quality management plan and quality matrix to determine our performance. This is making sure the procedure is doing what it needs to based out of actual data cause you are executing to ensure that the procedure is good. Quality audits, these are quality activities to make sure you comply with the company's policies, processes and procedures. Going back to your CMI or ISO, your project has to comply with those policies, processes and procedures in order to be compliant with the rest of the company. Process analysis, you are going to utilize that process improvement plan and you are basically trying to optimize the performance of those procedures. In summary, we have gone over the inputs which are the quality management plan, process improvement plan, quality matrix, quality control measurements, and project documents. The tools are the quality management and control tools, quality audits, process analysis. Your outputs are change requests, project management plan updates, project documentation updates, and organizational process assets. [/toggle_content]

Video Transcription

00:04
so not really finished the planning stage, but only had one process playing quality management.
00:09
Now we're gonna exit. Now we're gonna enter the executing states that were actually performing work. So it's perform quality assurance,
00:17
perform quality assurance validates the process, not the product.
00:21
So you're more concerned about making sure that the process is correct. You're not concerned about the product of this point.
00:28
This creates change. Your Quest
00:30
project management plan updates, um, and its input side of the quality management plan. What's we just created?
00:37
This, as you remember, provides details. Mythologies
00:41
apply to quality assurance.
00:43
Uh, continues, uh, continues process improvement.
00:49
Remember the process improvement plan? Uh,
00:51
so most in line with the project with the within the organization. So if you can imagine if your company's c m I r o p. M. Three,
01:00
you have certain processes that have to be met. Thio conform with how your company does business.
01:07
Quality metrics,
01:07
also just created from the previous, uh,
01:11
process, defines the characteristics and variables that are measured
01:15
and provides the details of acceptable variances.
01:19
So if you remember,
01:22
it's something. If your standard is 95% it's plus or minus 5%.
01:27
If it's 89% it fells. But if it's 90% it's within tolerance. It's fine.
01:34
Ah, or another example ifyou're tolerances,
01:38
uh, 90% plus or minus 5%. So you reach that 90% goal and you keep going. You reached 95%. You're still good.
01:48
You had a 96%. Now your gold plating because you're doing more than what was required.
01:53
Uh, quality control measurements is another employee
01:57
provides the quality criteria and the procedures.
02:00
So the tools for performed quality assurance,
02:05
our quality management and control tools
02:07
this he evaluates the data against the quality management plan and quality metrics
02:12
determine our performance.
02:15
So this is making sure that the procedure
02:19
is doing what it needs to based off of actual data because you're executing,
02:23
ah to ensure that the procedure is good
02:27
quality audits.
02:28
These are quality activities to make sure you comply with your company's policies, processes and procedures. So going back to if your Seema my or isil,
02:38
your project has to comply with those policies and processes and procedures
02:44
in order to be compliant with the rest of the company
02:47
process analysis,
02:50
so you're gonna utilize that process improvement plan and you're basically going to try to optimize the performance of those procedures.
03:01
So in summary, we've gone over the inputs which are the quality management plan, process improvement plan, quality metrics, quality control measurements and project documents.
03:12
The tools are the quality management and control tools, quality audits,
03:16
process analysis
03:17
and your outputs are changed. Requests,
03:21
project management plan updates, project documentation, updates
03:24
and uh, organisational process assets updates

Up Next

Project Management Professional (PMP) - PMI

Our online PMP training course educates on how to initiate, plan and manage a project, as well as the process behind analyzing risk, monitoring and controlling project contracts and how to develop project schedules and budgets.

Instructed By

Instructor Profile Image
Vince McKeown
Senior Program Manager at FGS, LLC
Instructor