  • #87754

    amenezes67
    Participant

    Both are KPI’s, both can measure the actual performance (physical) on the project.
    But…
    What happens when you reach dates beyond the original programmed completion date?

    Follow my posts, and we will discuss this matter deeper.

    Problem #1: After the baseline completion date, the SPI (EV/PV) or (BCWP/BCWS) only shows “How much of the planned work we achieved”, not the real Schedule Performance, as the name of the KPI is.
    So, when the actual date is beyond the baseline finish date, the indicator keeps rising.

    ——
    Tomorrow we’ll keep talking on this issue…
    Follow us.

    #87858

    amenezes67
    Participant

    Consider the table below:
    If you take a look at the SPI, even when you pass the baseline finish date… the SPI is rising.

    BCWS 24.00 40.00 63.00 107.00 133.00 150.00 189.00 230.00 231.00 231.00 231.00 231.00
    ACWP 22.80 36.72 57.09 96.81 120.92 133.57 155.52 179.60 191.64 209.07 240.00 250.00
    BCWP 21.60 33.43 51.17 86.63 108.83 119.57 148.90 182.48 192.00 205.00 226.00 231.00

    CPI 0.95 0.91 0.90 0.89 0.90 0.90 0.96 1.02 1.00 0.98 0.94 0.92
    SPI 0.90 0.84 0.81 0.81 0.82 0.80 0.79 0.79 0.83 0.89 0.98 1.00

    That’s why the SPI by itself is not good to measure the schedule performance after the baseline end of the project.

    #99582

    cybermo
    Participant

Viewing 3 posts - 1 through 3 (of 3 total)

You must be logged in to reply to this topic.

Our Revolution

We believe Cyber Security training should accessible for everyone, everywhere. Everyone deserves the OPPORTUNITY to learn, begin and grow a career in this fascinating field. Therefore, Cybrary is the world's largest community where people, companies and training come together to give everyone the ability to collaborate in an open source way that is revolutionizing the cyber security educational experience.

We recommend always using caution when following any link

Are you sure you want to continue?

Continue
Cancel